Purpose

Production Line Maintenance is used to record information about production lines, such as the standard production rate. If your company has multiple production lines, each dedicated to certain products, production is typically scheduled by line, rather than by item.

In Advanced repetitive, Line Schedule Workbench and Planned Repetitive Approve used the information from Production Line Maintenance, along with the shift schedule, to calculate daily production capacity.

 

Method

 

Production Line:  Enter the code of the Production Line to be defined.  The code is to match agreed Work Centres codes. 

Site:  Enter your site code

Press Enter.

Description:  Enter a short description of the production line. This would usually match the work centre description.

Units/Hour:  If all items produced at this production run at the same rate, enter  units per hour in this field. If they differ, leave this field blank and enter specific units/hour against the item number.

Enable Run Size: Enter Yes to enable a link between the run crew size and the run rate. When set to Yes, any modification to the run crew size on the production order causes the system to calculate the run crew productivity value.

Number of Lines: Enter the number of resources this production line represents. You can not enter zero.

Duration Buffer: Specify Duration buffer in days, hours, minutes and seconds.

Set Up Time: Specify Set up Time in days, hours, minutes and seconds

 Auto Firm: Specify Yes to have the system automatically firm orders scheduled at this production line. If Auto Firm is set to No, the system does not firm planned orders.

Scheduler ID: Optionally, enter ID of scheduler responsible for this production line.

 Horizon End: Specify either Day, Week or Month as the horizon end for this work centre. This field is only applicable when Planning & Scheduling Workbenches are enabled in Site Maintenance.

Period Number: Specify the number of periods to use for the scheduling horizon for this work centre, This field is only applicable when Planning and Scheduling Workbenches are enabled in Site Maintenance

Calculate Date: Automatically generated field.

Press enter of click on next to continue

 Item Number:  Enter the Part Number that is assigned to this Production Line.

Start Date:  Accept default start date unless setting up a future amendment.

Press enter of click on next to continue

Units/Hour:  This will either default from above, or needs to be entered against the item number.

Number of Lines: Enter the number of production lines for this item to be scheduled on. The default is 1, you can not enter zero.

Primary Line:  If this is the only Production Line on which this part will be processed, click on the box (which will create a check) for YES.  If it can be processed on multiple lines, leave it blank for NO.

Set up time: Specify Set up Time in days, hours, minutes and seconds

Setup Crew:  Leave blank.  Not used.  Reference only.

Size:  Leave at zero (0).  Used with Setup Crew.

Run Crew:  Leave blank.  Not used.  Reference only.

BOM Code: Enter a valid bill of materials for this item

Routing: Enter a valid routing for this item

Size:  Leave at zero (0).  Used with Run Crew.

Tool ID:  Leave blank.  Not used.  Reference only.

Run Sequence 1:  Leave blank.  Not currently used.

Run Sequence 2:  Leave blank.  Not currently used.

Comments:  Check for Yes if you want to add comments.  If not, leave blank.

Continue to add Part Numbers or click on BACK to complete the screen.

To delete this part from the Production Line, click on DELETE.